Ira Allen Chapel – Tower Work

What Is Happening?

We will be adding steel beams to the porch system at Ira Allen Chapel using a crane. We will also be painting the tower using a crane and basket.

Duration of Work:

Start of Work: Monday September 17, 2018
Completion Date: Friday September 28, 2018

What to Expect:

There will be no on-street parking on University Place, and the adjacent sidewalk will be closed. On street parking will be reserved for the crane in front of the Ira Allen Chapel.

Part of the street may be blocked off, so expect light traffic and delays due to one-way traffic.

Some noise due to crane and metal work.

Questions and Project Contact:

Scott Goodwin, Project Coordinator
Phone: 802-922-6336
Email: Sagoodwi@uvm.edu